Air source heat pump, solar PV and battery storage at Chulmleigh Pavilion

A 5kW air source heat pump with underfloor heating, 6.56kWp of rooftop solar PV and 5.3kWh of battery storage for the Chulmleigh Playing Fields Association.

Project overview

VIA Energy installed a 5kW Mitsubishi Ecodan air source heat pump with underfloor heating, 6.56kWp of rooftop solar PV and a 5.3kWh Sunsynk battery at Chulmleigh Pavilion, a community sports and recreation venue run by Chulmleigh Playing Fields Association.

Key results

6.56kWp

Solar PV system

5.3kWh

Battery storage

5kW

Air source heat pump

£164

Projected annual saving on heating and hot water

The property

Chulmleigh Playing Fields Association runs the pavilion on Leigh Road as a community sports and recreation venue, with a hall, meeting room, kitchen, changing rooms and a fitness suite. A new studio, officially opened on 30 May 2025, adds more space for community activities.

Property type

Community sports venue

Bedrooms

Floor area

Construction

Previous heating

Build period

Solar panels on the roof of Chulmleigh Pavilion with the outdoor heat pump unit beside the building

The solution

We installed a Mitsubishi Ecodan air source heat pump for space heating and hot water, with the first phase of underfloor heating, then added solar PV on the roof with a Sunsynk hybrid inverter and battery. The heat pump was commissioned on 12 May 2025 and the solar PV was installed on 2 June 2025. Our electrician completed the handover on site and set up the system monitoring on 22 July 2025.

Air source heat pump

5kW Mitsubishi Ecodan (PUZ-WM50VHA) providing space heating and hot water, with a 200-litre Joule cylinder. The first phase of underfloor heating uses a Maincor staple-and-clip system with 16mm pipework and digital room thermostats.

Solar PV

6.56kWp system of 16 DMEGC 410W panels on the pavilion roof.

Battery storage

5.3kWh Sunsynk battery with an 8kW three-phase Sunsynk hybrid inverter, so solar power generated during the day can be stored and used later.

Installation process

A well managed installation with minimal disruption to the household.

01

Initial consultation

Site survey, energy assessment and system design.

02

Design and planning

Detailed design, system specification and permissions if needed.

03

Installation

Professional installation by our in-house team.

04

Testing and handover

Full system testing, commissioning and handover.

05

Ongoing support

System monitoring, servicing and long term support.

Results and performance

The heat pump is projected to cut the cost of heating and hot water by about £164 a year, around 19%, compared with an oil boiler.

We estimated the building needs around 11,089kWh of heat a year: 9,291kWh for space heating and 1,798kWh for hot water. The proposal also allows for a second phase of underfloor heating, on its own manifold, in the future.

Annual bill saving

based on current usage

CO₂ saved per year

estimated

Less grid electricity

reduction in grid use

Project gallery

Click a photo to enlarge

What our client said

★★★★★

Interested in a similar project?

Tell us about your property and we’ll talk through your options, or call 01271 445515.

Could a grant cover part of the cost?

Many homes can use the government’s Boiler Upgrade Scheme towards a heat pump. We’ll check what applies to your property and handle the application.

News, projects and updates

Occasional emails about our latest projects and anything that could affect your energy costs.

Scroll to Top